Project Summary |
|
|
Peak Consulting Engineers, LLC* was appointed the primary consultant for The City of Reno to prepare plans and specifications for three separate sites requiring installation of storm water drainage improvements and appurtenances. The bulk of work required installation of 240 LF of 48" RCP to enclose a major drainage ditch between Reno High School and Idlewild Drive. The remaining two sites consisted of installation of manholes and storm drain pipe. Peak, acting on behalf of The City of Reno, prepared bidding documents, managed the project in relation to sub consultants, and approved all expenditures and payments. |
|
![]() |
| * Work performed while doing business as Uni-Tec Consulting Engineers, Inc |